Where do you set abbreviations for days and weeks

October 14, 2015 Q: Where do you set abbreviations for days and weeks We normally enter activity durations in weeks. Where do I set this and if possible can we change it the display from “weeks” to just “w” A: You can do this very easily in the Project Options. To Set the default time units for entering duration, go to Schedule>Settings and Options>Project Options>Duration tab and select the unit from Duration is entered in drop down list. To modify how the units appear, go to the Project Options> Units tab. There are a series of drop-down lists that allow you to select how the units are displayed. In your case, from the Weeks dropdown list select “w”. For more information please visit www.intaver.com http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1153