Q:Set Duration Units
Can I define project duration in minutes and how to do it?

A: Yes, you can set duration units from minutes to months. To set your duration to units:
1. Go to Project Options and click the Duration tab.
2. From the Duration is entered in: drop down list, select the unit. In this case it would be Minutes.
Please note that if your duration units are defined in Microsoft Project and you import schedule from Microsoft Project to RiskyProject, duration units will be imported as well. Also in RiskyProject Enterprise duration units can be different for different projects.

FOr more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=4&t=1260