Sunday 29 May 2016

Maximum Project Duration

May 25, 2016

Q: Maximum Project Duration
What it is maximum project duration and how it is used?

A: Maximum project duration is set in the Project Settings dialog box. The maximum duration can be set using days, months, or years. This setting creates a project deadline that is used during Monte Carlo simulations to measure the project success rate of meeting this deadline. Success rates can be viewed on the Success Rate view in the Analysis tab. The Project Deadline is shown as a vertical red line on the Gantt chart.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=4&t=1258

Image

No comments:

Post a Comment