Wednesday 30 December 2015

Project risk score scale

December 23 2015

Q: Project risk score scale
I saw a risk scale on the project summary diagram. What does it mean and how it is calculated?

A: Project risk score scale is presented when you perform calculation in Microsoft Project. It is part of project summary dialog.
When you double click on project bar in RiskyProject Enterprise, the same dialog will come up. Project risk score is calculated separately for duration, cost, and other parameters. If there are no uncertainties in cost and other parameters, risk score fields will be empty. Project risk score is calculated based on empirical formula: project risk score equals 2 if all risks increase project duration or cost two times. If project risk score is less than 1, it is an opportunity or cancellation, so due to risk and uncertainties project will cost less or take less time. Also please remember that project can be cancelled. In this case it will also take less time and cost less.

For more information visit: www.intaver.com
http://www.intaver.com/IntaverFrm/viewtopic.php?f=6&t=1200


No comments:

Post a Comment