Sunday 21 August 2016

Calendar exceptions in RiskyProject

August 16, 2016

Q: Calendar exceptions in RiskyProject
Can I define specific non-working days (calendar exceptions) in RiskyProject?

A: You can define any calendar exceptions in RiskyProject. To do it, click on Schedule -> Schedule and Calendar and then click on Calendar icon. Working time dialog comes up. You may now click on any working day and any day of the week and define non working time. You may define non-working hours within a day as well as you can define that full day will be non-working. If day is non working the day within a calendar will have a yellow strip above a date. You can also define that this date will be "Standard Working Time" (8 a.m to 12 p.m. and 1 p.m. to 5 p.m.), morning off (1 p.m. to 5 p.m.), afternoon off (8 a.m. to 12 p.m.), or 24 hours working day.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=3&t=1288

No comments:

Post a Comment