November 20, 2015

Q: User log in RiskyProject Enterprise
Can see how many people logged on and what changes did they make in the RiskyProject Enterprise?

A: RiskyProject Enterprise session log can be found in Files->Users->Logon History. It includes list of all activities and closed sessions with user name and computer ID, so you can see who logged on to the system and when. Administrator can delete sessions from the log. If logoff time is empty, it means that session is in progress of the user did not properly logged off (shut down computer or killed RiskyProject).
To see other information related to use activities you may use risk history: double click on risk ID, and then go to history tab. Administrators can edit these logs for all users, while users can edit only their own records. You cannot see any log if user changes schedules, or import schedule from Microsoft Project or Primavera to RiskyProject.

For more information please visit www.intaver.com

Risk Outcome Cancel Task and Successors

November 20, 2015

Q: Risk Outcome Cancel Task and Successors
What risk outcome "Cancel task and all successors" means if I have complex network and multiple paths?

A: If your define a risk and risk outcome is "Cancel Task + All successors", it would mean that this task will can cancelled and all successors of this tasks will be canceled at the same time with the same probability. In the example bellow risk is applied to the first task called "Risk1", but "Risk2" and "Risk3" will also be cancelled at the same time. Cancelation means that duration will be set to zero. Cost of cancelled task depends when cancelation event occurred and cost accrual rules. RiskyProject has a notion of moment of risk. Risk may occur any time during a course of activity. It is defined by statistical distribution. If risk occurred at the middle of activities and cost accrual is set to prorated, than RiskyProject will calculate cost as 50% of total cost. If risk outcome is "Cancel Task + All successors", the same rule will be applied to all successors of this task.
For more information please visit www.intaver.com

Low and high duration in Microsoft Project

November 20, 2015

Q: Low and high duration in Microsoft Project
Hi, we are evaluating RiskyProject and it seems that even though I changed estimates for low and high, it still seems to be calculating with previous numbers.

A: When you are using the RiskyProject Addin to run schedule risks analysis, there are a few key things to be aware of. You must identify the field that you will be using for the Low and High estimates in the Field Mapping. By default it is Text11, but can be any text field that is available. Once this is mapped, you should not change this setting as this is where the Addin looks to apply statistical distribution during the Monte Carlo simulation.
When you are first adding the low and high estimates, you must provide a statistical distribution by using the Input Distribution > Duration dialog box.
Once this is done, you can modify the Low and High estimates without using the dialog box. However , this will bypass any error checks that are done when you input the data, for example you cannot enter a low estimate that is greater than the base duration. Looking at your file, I found a few things that could be causing the issues you are seeing. If you are modifying the data without using Duration dialog box, it is possible to enter values in which Low > Base or High < Base or Low which could cause errors.
If you look at the image below, I have indicated a few issues in the data that should be addressed.

For more information please visit www.intaver.com

Saturday, 14 November 2015

November 9, 2015

Q: Restoring Links with Microsoft Project files
I have made a *.mpp project and from the MS project started the riskyproject application. However when I move both files I am not able maintain the link between the two program. What shall I do? Where can tie files together again?

A: The file linkage that you mention is based upon the location of the files. When you use the Addin to export the data from Microsoft Project to RiskyProject it creates a link in your registry that includes the file names. The link includes the path and name of both files for example c:\My Documents\Test.mpp=c:\My Documents\Test.alm.
The linkage feature only works if the location of the mpp file is the same. For example, if you move the mpp file location, when you export the data, RiskyProject will look to see if there is already a mapping saved in the registry. But because the file is moved, it will not find a match and it creates a new file, but it is now linked to the moved mpp file.
However if the data in the Microsoft Project file is the same and you can import your risks from your existing alm file as risks are linked using the task unique ID in Microsoft Project and these do not change even if you delete or add new tasks.
To import the risks, in RiskProject choose File (icon in the top left) > Import > Risks From Another Project. Browse to the original *.alm file and click OK to import the risks.

For more information please visit: www.intaver.com

http://www.intaver.com/IntaverFrm/viewtopic.php?f=3&t=1175


Wednesday, 11 November 2015

How do I sort out residual risk from uncertainties

November 9, 2015

Q: How do I sort out residual risk from uncertainties
We have created a mitigated baseline that contains both residual risk and uncertainty. As part of your process, we would like to separate out the impacts of the residual risks and the uncertainties from the monte carlo risk analysis. Is there a quick way to do this. We were thinking of creating to baselines one with the risks and one with only uncertainties, but would prefer not to.

A: The easiest way is just to disable all the risks. First step is to run a monte carlo simulation. Save the analysis. Then you can disable all the risks. This is done in the Risks Tab, Export/Import > Enable/Disable Risks.
Run one more simulation and record the results. This results of this analysis in the impact of uncertainty on your project. The differences between the 1st and 2nd simulation is the impact of the residual risk on your project.

For more information please visit www.intaver.com
http://www.intaver.com/IntaverFrm/viewtopic.php?f=4&t=1174

Is there any high level register summary

November 9, 2015

Q: Is there any high level register summary
Is there a quick way to see a summary of the risk register. Like how many risks, what is the cost of the risks etc.

A: Yes. #RiskyProject comes with a Risk Register dashboard. It is found in the main Risk Register view. To view it you must click the Statistics button. The Statistics dashboard provides a high level overview of the status of the risk register, including number of risks, status of risks (open, closed, issues etc). Last updates and cost of risks.

For more information please visit www.intaver.com

http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1173


Sunday, 8 November 2015

Monte Carlo simulation performance

November 3, 2015

Q: Monte Carlo simulation performance
As part of our project reporting, we have to provide schedule risk analysis on a monthly basis. Currently, the master schedule is over 10000 tasks and is resource loaded. We use the MS Project addin to export the xml to RiskyProject and the size of file now is over GB and is maxing out the computers memory etc. Do you have any tips to speed up the process. We can’t modify the file, so that is out of the question.

A: If the Addin is still exporting an xml file from MS Project, you must still be on version 5. In the latest version 6.x, we have replaced the xml format with a proprietary data file which allows us to automatically eliminate around 90% of the data transferred as it is not required for the schedule or cost risk analysis . In addition, users can customize the data transfer as well, by eliminating unneeded project data such as Notes, Custom Fields, Deadlines, and Cost (if you are only running schedule risk analysis.
(picture)
By eliminating extraneous data from the analysis, with the current version we have been able to improve the time required to export data and run a simulation from 10 to 30 times. This is a significant improvement and it means that analysis that used to take an hour can be done in minutes and what took minutes now only takes seconds.
See our news release at: http://www.intaver.com/riskyproject_version61.html

For more information please visit www.intaver.com
http://www.intaver.com/IntaverFrm/viewtopic.php?f=3&t=1170