Saturday 1 October 2016

Viewing statistical distribution for the project

September 25, 2016

Q: Viewing statistical distribution for the project
How do I see statistical distribution for project duration and cost without opening this project? I have many projects in portfolio and would prefer not to open them one by one.

A:
You don't need to reopen project when you want to see statistical distribution for project duration, finish time, and cost. First, make sure that project is calculated. Results of Monte Carlo simulations are saved in the database for each project. If project is calculated go to Project -> Portfolio Gantt and then right click on project ID. Select Project Details from drop down menu. The following dialog will come up: (see picture)
You can double click on each histogram to see details, such as enlarged chart, statistics, and raw data. Also you may double click on Gantt bar within a Portfolio Gantt view and present the same dialog with statistical distributions of project duration, finish time, and cost.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=6&t=1296

No comments:

Post a Comment