Saturday, 15 October 2016

Duration units

October 4, 2016

Q: Duration units
Can different task have different duration units?

A: The quick answer is no as the duration unit for activities is a global project setting (set for entire project). This is common to most (if not all) scheduling software.

The duration unit (hours, days, weeks etc.) are set in the Schedule tab> Settings and Options > Project Options > Duration.


For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1299

No comments:

Post a Comment