Define distribution for start time of the task

October 4, 2016

Q: Define distribution for start time of the task
Is it possible to set uncertainties for task start times?

A: Yes, however cases in which this can be used are limited such as the first activity in the project as otherwise start times are a product of the precedent network. To set uncertainty for start times on a activity, right-click on the activity ID and choose Task Information.

- In the General tab, set Low (early) and High (late) start times for the activity.

Click the Distributions tab.
- Select the Start Time sub tab.
- Select a distribution from the Distribution drop down list. The shape and parameters of teh charted in the Probability Density chart to the right.
- Depending upon the distribution type, you can modify parameters (e.g. Most Likely)
- Click OK to assign the distribution.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=4&t=1300