Q: Resource chart for portfolio
Can I allocate the same resource to different projects within project portfolio using RiskyProject Enterprise? Is it possible to view resource allocation to different projects on Resource chart?

A: In current version of RiskyProject Enterprise resources belong to only one project. You cannot share resources between different projects.
Resource peak units, allocation, work, or percent allocation for specific resource can be presented on the probabilistic resource chart. This is done for specific project only. So you would need to open project, perform Monte Carlo calculation of this specific project and than go to Schedule -> Resources. If you right click on resources you would select a particular information you would present on chart (units, work, etc.).
Essentially in RiskyProject Enterprise this chart works the same way as in RiskyProject Professional or Lite. You can view resource allocation associated with low, base and high project schedule. But please remember that this chart shows only allocation to current project.

For more information please visit: www.intaver.com