Sunday 20 November 2016

Viewing Project results for Work

November 15, 2016

Q: Viewing Project results for Work
Is it possible to create a chart that shows results for Work (#of hrs or effort) for the entire project?

A: Yes, if you have a resource loaded schedule, work for all resources, tasks, and the project is calculated during the Monte Carlo simulation.
To view Work for the entire project:

1. Run a simulation.
2. Open Analysis > Project Summary.
3. Click Statistical Data for Work (lower right). A chart showing the probabilistic results for work opens.

The chart can be a histogram, cumulative probability, or as in the example below, a combination of the two.
The work data or statistics can be copied for use in other programs by right-clicking and using shortcut menu.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1312

No comments:

Post a Comment