Wednesday 9 November 2016

How to disable low/high traingles on the Gantt chart

November 4 2016

Q: How to disable low/high traingles on the Gantt chart
How can I disable triangles depicting low and high estimates of task start and finish times in the Gantt chart within Result Gant View?
Project risk management, decision and risk analysis

A: The blue "triangles" are used to display low and high start and finish times for tasks. They are presented within Result Gantt view. Sometimes projects have a lot of uncertainties. In this case the chart can be very crowded, because these "triangles" can be very long. It is possible to disable these "triangles". To do it just right click on the Gantt chart. The drop down menu will come up. Then click on "Show Both Low/High Results". But default these "triangles" are enabled.

FOr more informarmation please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1309

No comments:

Post a Comment