Q: Scenarios analysis
What is the best way to compare multiple scenarios with different sets of risks?

A: If you are creating multiple alternatives with different sets of risks, we recommend using multiple baselines. Baselines are very flexible and allow you to create alternative project plans with different sets of risks and/or activities.

Once you have created your scenarios using baselines, you can use the Manage Baselines view (Schedule >Baselines > Manage) to see a high level comparison of each scenario using major project parameters.

If you require more detail comparison, you can generate specific risk reports for each baseline. You do this by setting a baseline as the Current baseline and then running analysis and generate specific reports required for your comparison.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1228