Sunday, 28 February 2016

Risk Register Report

February 25, 2016

Q: Risk Register Report
Is there a report for all risks in risk register?


A:  There are actually 2 reports that can fill the function. Which one you choose depends upon the information that you want to include.
In the Reports tab, the Report All Risks view allows you to generate a report that includes textual information about each risk. This can be very useful if you would like a quick overview of how the risk is assigned to various activities and resources. Some of our users use this report specifically when during reviews they need to defend/explain their assumptions behind the risk model. In the example below, the report illustrates how each risk has been assigned in a project. This is often used by projects that are using risk drivers, but are not managing the risks with the risk register.

The other risk report is found in the Risks tab. The Risk Report is suitable if you are managing risks, that is you have put risk plans using the risk mitigation waterfall chart in place along with status updates, etc. This report provides complete report on each risk of all the information that has been entered into the risk register. To create report, go to the Reports tab, Risk Report. To generate a report on all the risks in the register, highlight all of the risks.
To print out reports, go the File>Print. You can preview how it will be published using the Print Preview.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=3&t=1225



Image

Saturday, 27 February 2016

Low and high estimates for durations and costs

February 25, 2016

Q: Low and high estimates for durations and costs
We setup low and high estimates for the group of tasks. How to disable it?


A:  I am assuming that you mean that you selected a group of tasks and assigned low and high durations using coefficients. If this is the case, then you can reset the low and high estimates very easily.

Select the group of activities. Right-click on the task ID and click Set Low/High Duration. Now, click the Set low high durations equal base duration option. It works the same way for fixed cost. It is important to note that if you setup low and duration and cost manually, you can also use this process to clear low and high estimates.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1224

Image

User Permissions to Different Project

February 25, 2016

Q: User Permissions to Different Project
How do I assign user permissions to a specific project in #RiskyProject Enterprise?

A: First you must logon to RiskyProject Enterprise as an Administrator. You must have administrator permissions to make such changes. Once you are in RiskyProject go to File> User Administration.

You will see the Project Permissions tab. Open it and you will see the dialog which is separated into 2 lists, the Project hierarchy on the left and a list of users on the right. Now select the project to which you want to add the user and then select a user. You can select one or more users.
Click OK to save the changes.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=6&t=1223

Image

Wednesday, 24 February 2016

Width of the bar on the frequency chart

February 20, 2016

Q: Width of the bar on the frequency chart
Is width of the bar on the frequency chart for project duration associated with any particular time interval?

A: Width of the bar is defined by number of pixels and not associated with particular time interval. The same true for cost, start and finish time, work and other frequency charts. The bar width is defined in "Chart Options" dialog. To access chart options dialog right click on the chart and select "Options".
Maximum bar width is 30 pixels, minimum is 6 pixels. The issue is chart options are saved for all tasks and all project in the system registry or in the database of RiskyProject enterprise. Duration of the projects and tasks could be very different. If you define width of the bar in actual units (days, months, etc.) the histograms will look very different for different tasks and projects.


For more information visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=3&t=1222

Image

Sunday, 21 February 2016

Risk for rate

February 18, 2016

Q: Risk for rate
Is it possible to assign risk related to increase of rate for resources? For example, rate $10/hour can be reduced because of certain factors.

A: RiskyProject has risk outcome type called "Rate Increase". If this risk occurs, the rate for resource this risk is assign to will increase on certain value. To define rate risk outcome you need to select a resource, then you need to double click on resource ID. Then go to risk tab. Under "Outcome Type", you would need to select "Rate increase" and under "Outcome" enter a percentage of rate increase. You can enter a negative number as well. In this case it will be an opportunity.

Rate increase will lead to increase variable cost of all tasks this resource as assigned to. However units for resource assignment could be different for different tasks. In this case probability of resource risk will be reduced in accordance to the units.


For more information visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1220

Image

RiskyProject Enterprise on Individual Computer

February 18, 2016

Q: RiskyProject Enterprise on Individual Computer
Can I run RiskyProject enterprise on my personal computer without using server?
Top

A: Yes. If you evaluate RiskyProject Enterprise you can install it on individual computer. You can follow all instructions in RiskyProject Administrator guide. First thing you need to do is to install SQL Server database. It is possible to use SQL Server Express, which can be downloaded from Microsoft free of charge. RiskyProject supports all versions of SQL Server express starting from 2005. Please remember to install not only database itself, but also Management Studio. It simplifies working with the database.

Then install database by running RiskyProjectDB.exe. You will be presented with a dialog to configure a connection to the database:
You need to enter Server Name, which is defined when you configure SQL Server Express, logon credentials and database name. You can test connection to ensure that everything is properly configured. Then you need to install RiskyProject, select RiskyProject Enterprise and also configure connection to the database. The last step is not define a user. You will need only one user since you are running software on your personal computer. First time you logon to RiskyProject Enterprise you need to enter user name "sa". After this you will be prompted to enter new user name and password.

For more information visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=6&t=1221


Image

Saturday, 20 February 2016

February 17, 2016

Built On Vision is new Intaver Institute's technology parther

Built On Vision has become Intaver's new technology partner. "Built On Vision" is a cloud based software suite that provides leading edge project controls tools. "Built On Schedule" allows you to compare multiple schedules instantly so that you can identify trends and analyze issues. "Built on ProductivityTM" works with your ERP or costing system to mine cost and labor data for valuable analysis within your project allowing you to make targeted adjustments. "Built on Forecast" allows you to accurately forecast your project from anywhere while tracking communications about changes in real time and instantly comparing it to prior forecasts. "Built On Balance" gives you the power to leverage Line of Balance and render your schedule into a simple graph that eliminates the need to bring multiple reports into a CPM meeting.

http://www.builtonvision.com/