Q: NPV calculation
How can I calculate the project NPV?

A: NPV calculation is a feature of the Cashflow view. If your project has both costs and income, the Cashflow view will present a cash flow chart as well as the calculated NPV for both the original plan and with risks and uncertainties. To calculate the NPV enter a discount rate in the Discount Rate box. Once you have a discount rate, during the simulation, RiskyProject will calculate both the NOV and the IRR (Internal Rate of Return).

For more information visit: http://intaver.com/IntaverFrm/viewtopic.php?f=4&t=1323