Monday, 14 March 2016

Risk Categories and Alternatives

March 10, 2016

Q: Risk Categories and Alternatives
If a risk is assigned to different categories: 20% increase cost and 20% increase duration, is it considered to be alternatives or not?

A: Short answer is no. Risk alternatives are risk assignments within the same risk category. Take a look at the examples below. In the first the risk has been assigned to schedule and cost categories (Fixed delay an Relative cost increase respectively). We can see in the risk alternative pie chart shows only a single probability. In the second, we have added another risk assignment to the cost category. It is now shown as risk alternative 1 and 2 and this is now reflected in the pie chart.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1230

Image

Project risk alternatives

March 10, 2016

Q: Project risk alternatives
What happens if sum of probabilities of all alternatives are greater than 100%?

A: If you are using alternative outcomes to model a risk impact, then these means you have assigned the same type of risk outcome type (Cost, Schedule, etc.) for a single risk more than once as in the example below. In this example we have the same risk assigned to a task with the same risk outcome type (Schedule). There are four risk outcomes, each with 3% chance of occurring. If we look at the pie chart below we can see that overall the risk has a 12% chance of occurring.
Now what happens if the risk alternatives add up to more than 100%. In the example below, we have increased the first 2 alternatives to 70% and 50% respectively. If we add up all the risk chances, it should now equal 126%. However, risks can only have a probability between 0 <>100%. If the risk alternatives add up to greater than 100%, RiskyProject will add the risk alternatives and cumulatively add the probabilities until they reach 100%. In this example, we can see in the pie chart that now first risk with 70% chance will be fully accounted for. However, the second alternative will only add an additional 30% at which point the cumulative chance of the alternatives is now 100%. In addition the last 2 alternatives are ignored.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=3&t=1229

Image

Saturday, 12 March 2016

Scenarios analysis

March 3, 2016

Q: Scenarios analysis
What is the best way to compare multiple scenarios with different sets of risks?

A: If you are creating multiple alternatives with different sets of risks, we recommend using multiple baselines. Baselines are very flexible and allow you to create alternative project plans with different sets of risks and/or activities.

Once you have created your scenarios using baselines, you can use the Manage Baselines view (Schedule >Baselines > Manage) to see a high level comparison of each scenario using major project parameters.

If you require more detail comparison, you can generate specific risk reports for each baseline. You do this by setting a baseline as the Current baseline and then running analysis and generate specific reports required for your comparison.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1228

Image

Cash Flow Uncertainties

March 3, 2016

Q: Cash Flow Uncertainties
How can I view statistical distribution of cost for specific period of time? Can I use cash flow chart for it?

A: If you want to characterise cost as including both cost and income, then you can use the Cash flow analysis to view cost for specific periods.
To do this, run a simulation and then open the Cash flow chart. On the left you will see the cash flow periods and the right is the cash flow chart.

You can modify the periodicity using the drop down menu on the bottom of the view. Periods can be monthly, bi monthly, quarterly, and yearly.
Select a period from the table on the left and right-click on the number (1,2,3 ….). On the shortcut menu, click Results for selected Interval.
The Results chart appears. You can choose a histogram, cumulative probability or both. As with all charts, these can be copied or saved.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=4&t=1227


Image

Statistical distribution for lag

March 3, 2016

Q: Statistical distribution for lag
Can I assign risk event to lag? How to assign statistical distribution to lag?

A: You cannot assign a risk directly to a lag however, you can assign a statistical distribution to lag between predecessor and successor. This uncertainty in the duration of the lag is then accounted for during the Monte Carlo simulation.
To assign uncertainty to lags, open the Task Information dialog box and click the Predecessors tab. Here you can set lags. By default it is zero, but you can assign Low, Base, and High estimates for the lag If you enter low and high estimates, you must also select a distribution type.

For more information please visit: http://www.intaver.com/IntaverFrm/viewtopic.php?f=2&t=1226

Image

Sunday, 6 March 2016

New webinar "Mastering risk analysis with RiskyProject" on March 8, 2016

March 6, 2016

New webinar "Mastering risk analysis with RiskyProject" on March 8, 2016

Please joint us for webinar "Mastering risk analysis with RiskyProject". The standards for effective planning and management of projects are increasingly adopting Monte Carlo project risk analysis as an essential tool in an environment that is characterized by increased complexity and lowered risk tolerance. This webinar will show you a step by step process how to:
  • - Import project plans from other scheduling software
  • - Add uncertainty and risk events
  • - Understand how to analyse the results
  • - Generate key project risk analysis reports
To register for webinar please click here: https://attendee.gotowebinar.com/register/3597688179400315906


Built On Vision is new Intaver Institute's technology parther

February 29, 2016

Built On Vision is new Intaver Institute's technology parther

Intaver Institute will present paper "Project Schedule Risk Analysis with Events and Event Chains" on PMS 2016 - the 15th International Conference on Project Management and Scheduling. PMS 2016 will take place in Valencia, Spain, from April 19th until April 22nd. It is organized by the Universitat Politècnica de València and by the Universitat de València. PMS is an international conference series devoted to Project Management and Scheduling. It was inaugurated by the European Working Group on Project Management and Scheduling (EURO - EWG Project management and scheduling).

http://www.intaver.com/index-news.html
http://www.pms2016.com/